Project Construction Updates

The project is currently under review for a Conditional Use Permit and more information can be found here: Conditional Use Permit Page

Planning Commission meeting February 4th, 2026 Meeting Agenda

Construction is expected to begin in late Spring 2026. Regular updates will be posted on this site including time-lapse videos of the construction.


The property was acquired for ODOT in July of 2021. Scott Edwards Architecture began preliminary design in February of 2023 moving into final design in August of 2024. The City pursued a Construction Management/ General Contractor (CM/GC) procurement process to streamline the construction design and ultimate construction of the facility by incorporating General Contractor early in the process. Skanska was awarded the GM/GC contract in June of 2025. A full list of City Council updates and presentations can be found on the Key Dates section of this webpage.

Share Project Construction Updates on Facebook Share Project Construction Updates on Twitter Share Project Construction Updates on Linkedin Email Project Construction Updates link
#<Object:0x00007fe9029404b0>